Anglia Square demolition to finish by year-end with work extending to May 2027
Summarised from 2 outlets · Updated 7 Nov, 07:20 · Archive
Demolition of Norwich's Anglia Square shopping complex is expected to finish by year-end, but remediation work will continue until May 2027.
Demolition of Norwich's Anglia Square shopping complex began in February and is expected to finish by year-end. The former 1960s shopping centre, car park and associated buildings will then undergo six months of remediation and site-clearance work, with contractors DSM Demolition remaining on site until May 2027.
The project has experienced several setbacks. Asbestos was discovered and removed during the summer, and human remains were unearthed approximately ten months into the demolition programme.
Norwich City Council, which is leading the £350m redevelopment of the site, stated that the remediation works have always formed part of the project and do not represent additional delay. A council spokesman said the six months of site-clearance work would run alongside the wider scheme and would not delay construction of 1,100 homes. Building work is likely to start by year-end or early next year.
However, videographer Wayne Stuart, who has been documenting the project, reported that DSM contractors refused to specify when construction of the homes would begin.
How it is being reported
- Anglia Square remediation works to take six months on top of already delayed projectAnglia Square demolition in Norwich is expected to finish by year-end but DSM Demolition will continue remediation until May 2027.Norwich Evening News · 7 Nov, 06:00
- Anglia Square remediation works to take six months on top of already delayed projectAnglia Square demolition in Norwich is expected to finish by year-end but DSM Demolition will continue remediation until May 2027.Eastern Daily Press · 7 Nov, 06:00
In this story: Norwich City Council · DSM Demolition · Norwich · Anglia Square
This summary was written by AI from the headlines and standfirsts above, and states as fact only what at least two outlets report. How we use AI · Report a problem · Corrections log