Brighton Main Line to close for nine days in February 2027

Summarised from 2 outlets · Updated 10 Nov, 21:01 · Archive

The Brighton Main Line will close for nine days from 13 to 21 February 2027 for major engineering works.

The Brighton Main Line between Three Bridges and Brighton or Lewes will close from Saturday, 13 February to Sunday, 21 February 2027 for major engineering works. The closure falls during the February half-term holiday period. Buses will replace trains on affected routes, though passengers travelling between Brighton and Hove and Gatwick Airport or London are being encouraged to use train replacement buses rather than diverting to other transport. A direct service between Brighton and London Victoria will be diverted via Horsham and Littlehampton, extending journey times.

The planned work includes replacing rails at Plumpton and Preston Park, renewing track, switches and crossings at Keymer Junction, and strengthening cuttings at Haywards Heath and Balcombe to reduce the risk of landslips and rock falls. Balcombe Tunnel will undergo structural work and new rails will be installed through Clayton Tunnel. A new conductor rail supplying power to trains will be installed between Clayton Tunnel and Preston Park, alongside new signalling and renewed level crossings at Spatham Lane and Hamsey.

Network Rail and train operators are urging passengers to plan ahead and allow extra time for journeys. Online journey planners will show revised train and replacement bus times later this month.

Brighton Main Line to close for nine days in February 2027
Image: The Argus

Comments (0)

How it is being reported

In this story: Brighton Main Line · Network Rail · Three Bridges · Brighton · Lewes · London Victoria

This summary was written by AI from the headlines and standfirsts above, and states as fact only what at least two outlets report. How we use AI · Report a problem · Corrections log