Merseyrail Northern Line reopens after £3.5m tunnel work

Summarised from 2 outlets · Updated 7 Nov, 11:13 · Archive

The Merseyrail Northern Line between Hunts Cross and Liverpool city centre has reopened after nearly four weeks of closure for major tunnel waterproofing work.

Merseyrail's Northern Line has fully reopened after nearly four weeks of disruption caused by major engineering works. Network Rail invested £3.5 million to strengthen and waterproof four underground Victorian-built tunnels running beneath Liverpool city centre between Brunswick and Liverpool Central stations. The work was necessary to protect the third-rail system, which powers the electric trains.

More than 50 workers carried out extensive repairs since 11 October. They removed 92 cubic metres of concrete, drilled 6,500 holes for waterproofing injections, and created 115 drainage holes to direct water away from the tunnels. A total of 1,688 square metres of tunnel wall were treated to prevent moisture from compromising the power system. Paul Owen, Liverpool area director at Network Rail, said the investment protected 'the third-rail system which powers Merseyrail's electric trains' and was 'part of our ongoing investment plan and commitment to run a reliable railway for the future'.

Power control systems were also upgraded across both the Northern and Wirral lines during four extended Sunday closures. These improvements will allow engineers to isolate and switch off sections of the electrified rail more efficiently, enabling faster and safer maintenance in future.

Merseyrail Northern Line reopens after £3.5m tunnel work
Image: Liverpool Echo

Comments (0)

How it is being reported

In this story: Merseyrail · Network Rail · Liverpool · Hunts Cross · Liverpool Central · Brunswick

This summary was written by AI from the headlines and standfirsts above, and states as fact only what at least two outlets report. How we use AI · Report a problem · Corrections log