Tipton council flats plan delayed by year after builder collapse
Summarised from 2 outlets · Updated 13 Nov, 06:09 · Archive
A 55-flat council housing project in Tipton will not be completed until summer 2028, a year later than planned, after construction firm Torsion filed for administration.
A multi-million-pound move to build 55 new council flats in Tipton town centre will be delayed by at least a year after the collapse of construction firm Torsion. Sandwell Council has appointed Speller Metcalfe to take over the project on Union Street, with work now not expected to finish until summer 2028, rather than the originally planned summer 2027.
The ageing blocks of council flats in Union Street were demolished two-and-a-half years ago, with work beginning in earnest in August 2025. However, little progress was made after the groundbreaking ceremony, and Torsion filed for administration in July this year.
Council member Matt Lloyd, who represents Tipton Green, welcomed the appointment of the new contractor. He said: 'In July when Torsion went under, my inbox was quite full of concerns from residents about the future of all of this so I think it's really good that I can go back to them with this news today.' Separately, a former Conservative Club nearby is being converted into 15 new council flats by McPhillips, with work expected to be finished by the end of next year.

How it is being reported
- Tipton council flats plan facing at least year-long delayThe firm expected to build the 55 flats by next summer went bust and a new contract has been appointedBirminghamLive · 13 Nov, 05:30
- Multi-million-pound flats plan facing delay of at least a year after company files for administrationSandwell Council said the work to build 55 new flats in Union Street, Tipton, will not be finished until summer 2028Express & Star · 13 Nov, 03:00
In this story: Sandwell Council · Tipton · Torsion · Speller Metcalfe · Matt Lloyd · McPhillips
This summary was written by AI from the headlines and standfirsts above, and states as fact only what at least two outlets report. How we use AI · Report a problem · Corrections log