Sellafield plans facility for radioactive waste from 1950s

Summarised from 2 outlets · Updated 13 Nov, 06:09 · Archive

Sellafield has proposed a new radioactive waste handling facility to process sludge accumulated since the 1950s.

Sellafield Ltd has submitted plans to Cumberland Council for a new radioactive waste handling facility called the Sludge Handling and Export Plant (SHEP). The facility would process approximately 1,500 cubic metres of radioactive sludge recovered from the First Generation Magnox Storage Pond, an open-air pond constructed during the 1950s and 1960s that originally received irradiated nuclear fuel.

The proposed building would measure approximately 47 metres long, 28 metres wide and 21 metres high, occupying a footprint of around 1,300 square metres. It would be built alongside the existing Sludge Packaging Plant 1. Early work could begin in 2029, with the facility expected to begin operations around 2040.

Sellafield Ltd has requested an Environmental Impact Assessment screening opinion to determine whether a full environmental assessment is required. The facility would receive sludge through connecting pipelines, concentrate it by allowing solids to settle and removing liquid, then transfer the material into 500-litre drums for transportation to the Waste Encapsulation Plant for further treatment and interim storage elsewhere on the Sellafield site. The project is currently at an early feasibility stage and has not yet been fully developed or approved.

Sellafield plans facility for radioactive waste from 1950s
Image: Whitehaven News

Comments (0)

How it is being reported

In this story: Sellafield · Cumberland Council · Sellafield Ltd · First Generation Magnox Storage Pond

This summary was written by AI from the headlines and standfirsts above, and states as fact only what at least two outlets report. How we use AI · Report a problem · Corrections log